Removing the Existing GOSP-4’s Gas Absorber and Reinstall it Instead of GOSP-6’s Gas Absorber at Nafoora Field
It is a turn key project consisting of removing existing Gas Absorber located at GOSP 4 and reinstalling it at GOSP 6 location.
BPC’s responsibilities are Engineering, Construction, Pre-Commissioning and Assistance to Commissioning.
Project requirements include development of engineering documentation c/w construction drawings, QA/QC and project management documentation.